|
Written by Dave Grennan
|
A log of my journey while building my observatory. This project
is currently a work in progress as of June 19th 2006. Please
click the 'read more' link below regularly to see updates as they
happen.
Introduction
For many years I have dreamed of having my very own observatory. Here in
Dublin, Ireland clear nights are not so plentiful, so when a good clear
transparent night arrives, it is essential to make the absolute most out of
it. Many times I have spent an hour dragging out telescopes, computers,
CCD equipment etc only for it to cloud in just as I was about to begin shooting
some frames. Other nights I simply didnt set up because I felt the weather might
close in. Often those nights remain clear. It was clear to me that
the only way around this problem was to build a permanent observatory.
With such a facility in place I could make so much more of the limited clear
skies. Just as importantly I could be doing some real astronomy rather
than spending all my time setting up and breaking down equipment. Having a
structure around me would also mean I could be doing astronomy on nights that I
might have considered too windy otherwise.
In May 2006, I finally decided that with the short summer nights here it was
time to make that dream a reality. The first decision was what sort of
structure to build. That was an easy one. A shed with a roll off
roof was not only going to be inexpensive but also well within my constructional
capability. Luckily I had some good help, my good friends Carl O'Beirnes
and Gary Clarke were more than willing to lend a hand Gary is a builder by
profession so his help was going to be invaluable. I decided an 8ft x 10ft
structure would easily meet my needs.
The Pier
The first step was to construct the pier. To build this pier I began by
digging the father and mother of all holes. around 5 feet deep and four feet
wide was a much bigger job than it sounds! With the hole dug, I placed an
9 foot lenght to 11inch PVC sewer pipe in place. I then poured about a
foot and a half of concrete around the base and let it set. I then
backfilled the hole with earth which had been dug out, compressed it down
leaving another two feet on top. This final two feet was filled with
cement as was the sewer pipe itself. The final part of that job was to
insert four 12 inch long M12 bolts into the wet concrete. This will act as
the mounting points for steel plates which will eventually support the mount.
 |
This photo shows the pier structure after cementing. I
laid a border of 2" concrete slabs around where the base of the
structure will go and cenented them in place. I then filled the
center with concrete too. When the structure is almost finished, the
plan is to fill fine sand and cement to make a very level floor.
This will then be overlaid with rubber matting to provide the final
flooring. |
Beginning the Structure.
| On Saturday June 10th, 2006 the construction of the main
structure began in earnest. With the help of Gary and Carl the main
'studding was constructed for the four sides. 4 x 2 timber were used for
this stage |
 |
 |
Here the studding has been built and assembled. The
front stud is slightly lower than the rear. This is to accomodate 4
x 3 beams to support the rolling roof. |
| The stud frame is now clad with 6 x 1 timber. When
finished the gaps will be sealed with silicone, covered in sheet plastic
and an outer skin of either treated ply or aluminium sheet will be applied
(it really depends on whether I can get shiplapped aluminium cladding cost
effectively). You can also see that 4 x 3 beams are now in place on
top of the main structure to support the rolling roof. AT this stage
the frame has not been secured into the ground but you would move this now
no matter how hard you try. |
 |
 |
A wide shot showing progress to date. The main four
walls are in place as are two 20ft long 4 x 3 beams. The beams are
held temporarily by the 6 x 1 at left. Next job is to build the
roof. |
The Roof
| The roof is a fairly standard job. Three 4 x 2 lenghts
are screwed together to make the main beam up top. The trusses are
screwed in using aluminium 'roof hangars'. Inset into the base of
the roof are recessed roller bearings, each with a load rating of
100lbs. With 10 roller bearings used that should just about take the
weight ;-)
The roof is shown here covered with a skin of PVC sheet as the first
layer of damp proofing. The next stage is to cover the roof in
treated ply, then apply another layer of PVC and then finish with a double
layer of 'torch on' felt.
It is, of course, absolutely essential that the observatory is totally
damp proof. All of the walls will be double layered with PVC. The
spaces between the studs filled with insulation and a skin of hardboard on
the inside will give the inside a finished look.
|
 |
 |
June 19th: The four walls are up roof frame is built
(and slides along the 4 x 3 beams). The 4 x 3 beams will be fitted
with a layer of formica to make the roof roll a lot smoother. You can see
two 4 x 3's under the rails here temporarily. The next step is to
make 'risers' for these supports so the prodruding beams can be levelled
initially and also periodically in case of any sagging. |
|